    Chilled Water Plant Expansion — MEP Coordination

    LOD 400 MEP coordination for a chilled water plant capacity expansion tied into an active utility loop serving a critical infrastructure campus.
    Chilled Water Plant ExpansionSouthwest USQ2 2025 – Q3 2026
    12,000tons
    Capacity added
    28
    Tie-in points
    8
    Trades
    0 hrs
    Loop downtime
    Chilled Water Plant Expansion — MEP Coordination
    Mission Critical & UtilitiesRepresentative Project

    The challenge

    What we were solving for.

    All twenty-eight tie-ins had to occur on a live chilled water loop with no permitted loss of cooling capacity.

    Routing for the new chillers competed with existing risers, electrical gear, and structural bracing.

    Our approach

    How BimCon delivered.

    • Captured the existing plant and tie-in zones with terrestrial scanners and built a verified-as-built reference model.
    • Coordinated new piping, pumps, and electrical service against confirmed clearances with weekly clash reviews.

    Scope of work

    What BimCon delivered.

    • BIM coordination

      Multi-trade clash detection, weekly cadence, published issue log and resolution tracking.

    • MEP detailing

      LOD 400 fabrication-level modeling for mechanical, electrical, plumbing, and process trades.

    • Scan-to-BIM modeling

      Verified-as-built Revit model authored from the registered point cloud at the agreed LOD.

    Deliverables

    In your hands.

    • Federated Navisworks model
    • Clash detection & coordination reports
    • BCF issue log with resolution tracking
    • LOD 400 fabrication models per trade
    • Fabrication / shop-drawing support package
    • Scan-to-BIM Revit model at agreed LOD
    • LOD 350 verified-as-built deliverable

    By the numbers

    Project metrics.

    12,000tons
    Capacity added
    28
    Tie-in points
    8
    Trades coordinated

    Have a project like this?

    Send us your scope and we'll respond within one business day with a quote and a timeline.

    Request Project Review

    Response within one business day.

    Confidential · NDA-ready · Nationwide deployment