Advanced Logic Fab — Sub-Fab Process Coordination
Sub-fab process piping and utility coordination supporting a multi-billion-dollar fab build-out. Daily coordination cadence during tool install campaign.
Semiconductor FabSouthwest USQ3 2025 – ongoing
180,000 sf
Sub-fab area
60+
Process services
300+
Tool hookups
0 days
Tool-install delay
Semiconductor & CleanroomRepresentative Project
The challenge
What we were solving for.
Sub-fab routing for 60+ process services had to land within millimeter tolerances around tool drop locations whose footprints were still being finalized.
Concurrent tool installs required a daily coordination cadence with no margin for rework underneath live process tools above.
Our approach
How BimCon delivered.
- Captured existing slab penetrations and embeds at 2–4 mm accuracy and rebuilt them as a verified-as-built reference model.
- Detailed process piping, exhaust, and chemical distribution to LOD 400 with hanger and seismic bracing in coordination with structural.
- Ran twice-daily clash sweeps during tool install windows and published a same-day issue log to all trades.
Scope of work
What BimCon delivered.
Scan-to-BIM modeling
Verified-as-built Revit model authored from the registered point cloud at the agreed LOD.
MEP detailing
LOD 400 fabrication-level modeling for mechanical, electrical, plumbing, and process trades.
BIM coordination
Multi-trade clash detection, weekly cadence, published issue log and resolution tracking.
Deliverables
In your hands.
- Scan-to-BIM Revit model at agreed LOD
- LOD 350 verified-as-built deliverable
- LOD 400 fabrication models per trade
- Fabrication / shop-drawing support package
- Federated Navisworks model
- Clash detection & coordination reports
- BCF issue log with resolution tracking
By the numbers
Project metrics.
180,000 sf
Sub-fab area
60+
Process services
300+
Tool hookups
Services on this project
Capabilities delivered.
Related work
More from Semiconductor & Cleanroom.
Have a project like this?
Send us your scope and we'll respond within one business day with a quote and a timeline.
Request Project Review
Response within one business day.
Confidential · NDA-ready · Nationwide deployment